Weekly newsletter from the Särmä business and service centre construction site (week 18)
Jatke Toimitilat Oy has published the weekly newsletter for the Särmä business and service centre construction site for week 18. We will continue to distribute newsletters whenever new work phases begin at the construction site or when the construction work has an impact on, for example, mobility in the surrounding area.
In week 18, the work phases already underway will continue:
- foundation and local casting work
- element installation
- external water and heat insulation
- building perimeter fillings.
We apologise for any temporary traffic and noise disturbances.
Particular attention should be paid to
Observe the no parking signs in the vicinity of the construction site. Cars parked incorrectly in the area may be towed away at the owner’s expense.
The route to the library between the construction site and the library is closed with gates until further notice. The alternative route replacing the closed route is shown in the image below. Other routes and access to the library’s return box are open as normal.
There is heavy traffic, including articulated lorries, on Autoasemankatu and Hyryläntie near the construction site. Please follow the traffic instructions and road signs.
Transport and traffic
Access to the properties will remain open throughout the construction project. Please follow traffic signs and recommendations.
Renovation work on municipal infrastructure on Autoasemankatu in Tuusula will bring changes to traffic arrangements.
Please note that only library maintenance vehicles and vehicles travelling to LE parking spaces are permitted in front of the library.
For matters related to the construction site, please contact Rauli Kinnunen, rauli.kinnunen@jatke.fi.