Weekly newsletter from the Särmä business and service centre construction site (week 26)
Jatke Toimitilat Oy has published the weekly newsletter for the Särmä business and service centre construction site for week 26.
Work phases underway in week 26:
- foundation and local casting work
- element installation
- external water and heat insulation
- building perimeter fillings
- roof insulation work
- lightweight element installation on facades
- in-house production.
We apologise for any temporary traffic and noise disturbances.
Particular attention should be paid to
Observe the no parking signs in the vicinity of the construction site. Cars parked incorrectly in the area may be towed away at the owner’s expense.
There is heavy traffic, including articulated lorries, on Autoasemankatu and Hyryläntie near the construction site. Please follow the traffic instructions and road signs.
Transport and traffic
Access to the properties will be available throughout the construction project. Please follow traffic signs and recommendations. If necessary, traffic controllers will direct traffic.
The route to the library between the construction site and the library is closed with gates until further notice. Other routes and access to the library’s return box are open as normal. The new route to the library through the closed area is shown in the picture.
Please note that only library maintenance vehicles and vehicles travelling to LE parking spaces are permitted in front of the library.
For matters related to the construction site, please contact Kaisa Koivu, kaisa.koivu@jatke.fi.