Weekly newsletter from the Särmä business and service centre construction site (week 28)
Jatke Toimitilat Oy has published a weekly newsletter for the Särmä business and service centre construction site for the week beginning 7 July.
Work phases in progress during week 28:
- local casting work
- lightweight element installation on facades
- external water and heat insulation
- building perimeter fillings
- roof insulation work
- in-house production.
The demolition of the tower crane will take place on site from Wednesday to Friday.
We apologise for any temporary traffic and noise disturbances.
Particular attention should be paid to
Observe the no parking signs in the vicinity of the construction site. Cars parked incorrectly in the area may be towed away at the owner’s expense.
There is heavy traffic, including articulated lorries, on Autoasemankatu and Hyryläntie near the construction site. Please follow the traffic instructions and road signs.
Transport and traffic
Access to the properties will be available throughout the construction project. Please follow traffic signs and recommendations. If necessary, traffic controllers will direct traffic.
The route to the library between the construction site and the library is closed with gates until further notice. The new route to the library through the closed area is shown in the picture. Other routes are open as normal. The library return slot is next to the main door of the library.
Work on the surface parking area in front of the library will begin during week 28 with traffic arrangements and fencing.
Please note that only library service vehicles and vehicles travelling to LE parking spaces are permitted to drive in front of the library.
For matters related to the construction site, please contact Rauli Kinnunen, rauli.kinnunen@jatke.fi.