The route of the natural gas transmission pipeline is being altered due to a road project in the municipality of Tuusula and changes in land-use requirements. The route will be altered over a distance of approximately 800 metres.

Construction work on the new route will begin in May. The work is due to be completed in late autumn 2026.

Excavation work from May to September

The change to the route will require excavation work to be carried out between May and September on both sides of the Tuusula Eastern Corridor.

Gasgrid is acting as the project developer for the renovation work. Virén-Yhtiöt Oy has been appointed as the main contractor; the site contact is Mika Asikainen, 040 487 4858.

Feedback regarding construction work and the development of the area can be submitted via the online service.