Current construction sites

Car Station Street

We are constructing a new water main and storm water line on Autoasemankatu in Hyrylä, between Tuusulanväylä and Koskenmäentie. The construction will cause traffic disruptions.

The construction site is self-managed.

Study path

We are constructing a new light traffic route and lighting between Nukarintie and Kappalaisenkaari in Jokela.

The construction site is self-managed.

Riverbank

Joenranta is a new residential area being built in Kellokoski on the border between Tuusula and Mäntsälä. We utilise low-carbon solutions in construction and material selection.

The contractor is VM Suomalainen.

Coating work

Asfalttikallio will be responsible for the paving work in 2025. For more information about the paving work, please visit the Street paving work page.

Renovation of Agusta Park

The park’s renovation will include replacing the playground and exercise equipment, removing invasive species and replanting vegetation. A brush pile will also be built in the park from the stems and branches of the rowan trees that are being removed, much to the delight of insects. Rowan is an invasive species that spreads easily in the wild.

The park will be completed by the end of June 2025.

Puuha Group Oy is acting as the contractor.

Important information for people travelling near the construction site

Please note the following:

  • The construction site will be closed to public traffic and access by unauthorised persons will be prohibited. Where necessary, alte ative and safe detour routes will be arranged to replace the closed routes.
  • Advance wa ing signs are used to wa of mobile and/or small short-term work sites. When passing these, pedestrians must exercise caution.
  • The construction site may affect existing lighting, and street lights may be darkened over a wider area than just the construction site.
  • Noise, dust and vibration nuisance is possible during the construction work.
  • There will be open trenches in the work area during the work. However, no unprotected trenches will be left on the work site at the end of the working day.
  • When water pipe connections are being made, the water supply may be temporarily interrupted. Information about interruptions will be provided in advance.
  • Please also note the construction traffic in the area.

Give feedback on work sites

Feedback on construction sites can be provided through centralised customer service.

News on this topic

News

Public consultation on the planning of the Tallinn Tunnel freight line and the Kiila circular economy area on 24 November

You are invited to a joint event organised by Tuusula, Vantaa, and the Uusimaa Regional Council, where current plans will be presented and the views of residents and local stakeholders will be heard to inform further planning.  
A train on the tracks

A traffic park for younger family members to practise their road safety skills

Take a look at the plans for the traffic park being designed as part of the Tuusula Sports Centre, which features contributions from children and young people, and submit your feedback by 25 November 2026!
Two children are riding pedal cars.

Paths and benches are being refurbished in Kariniemenpuisto Park in Kellokoski

The refurbishment work will begin in week 46. The work is expected to last until late November.
Kariniemenpuisto is marked on the map with a red oval.