Excavation, construction site

Current construction sites

Car Station Street

We are constructing a new water main and storm water line on Autoasemankatu in Hyrylä, between Tuusulanväylä and Koskenmäentie. The construction will cause traffic disruptions.

The construction site is self-managed.

Study path

We are constructing a new light traffic route and lighting between Nukarintie and Kappalaisenkaari in Jokela.

The construction site is self-managed.

Riverbank

Joenranta is a new residential area being built in Kellokoski on the border between Tuusula and Mäntsälä. We utilise low-carbon solutions in construction and material selection.

The contractor is VM Suomalainen.

Coating work

Asfalttikallio will be responsible for the paving work in 2025. For more information about the paving work, please visit the Street paving work page.

Renovation of Agusta Park

The park’s renovation will include replacing the playground and exercise equipment, removing invasive species and replanting vegetation. A brush pile will also be built in the park from the stems and branches of the rowan trees that are being removed, much to the delight of insects. Rowan is an invasive species that spreads easily in the wild.

The park will be completed by the end of June 2025.

Puuha Group Oy is acting as the contractor.

Important information for people travelling near the construction site

Please note the following:

  • The construction site will be closed to public traffic and access by unauthorised persons will be prohibited. Where necessary, alte ative and safe detour routes will be arranged to replace the closed routes.
  • Advance wa ing signs are used to wa of mobile and/or small short-term work sites. When passing these, pedestrians must exercise caution.
  • The construction site may affect existing lighting, and street lights may be darkened over a wider area than just the construction site.
  • Noise, dust and vibration nuisance is possible during the construction work.
  • There will be open trenches in the work area during the work. However, no unprotected trenches will be left on the work site at the end of the working day.
  • When water pipe connections are being made, the water supply may be temporarily interrupted. Information about interruptions will be provided in advance.
  • Please also note the construction traffic in the area.

Give feedback on work sites

Feedback on construction sites can be provided through centralised customer service.

News on this topic

News

Survey for businesses in the retail and service sectors in the Hyrylä area

A survey aimed at businesses in the Hyrylä area to lay the groundwork for a new collaboration model has now begun. Entrepreneurs, share your ideas and thoughts by 21 June 2026!
Companies
Aerial view of Hyrylä town centre

Ground investigations are being carried out along the route of the East Railway

Fieldwork relating to the general planning phase of the Eastern Railway will commence along the entire length of the line. The route runs for a short distance through the southernmost parts of the municipality of Tuusula.
The railway line south of Jokela station

Keusote is seeking a food kiosk operator for the new Tuusula social and health services centre

The Central Uusimaa Welfare Region (Keusote) is seeking an entrepreneur to set up and run a food kiosk at the planned Tuusula social and health services centre. The centre is due to open in early spring 2029.
Illustration of the facade of the social and health centre

This content has been translated using AI